The authorities of the Belgian region of Wallonia have ordered the suspension of construction of a large Google data processing center due to the lack of permission to implement the modified project. By the time the regional authorities intervened, the main structures of the building with an area of about 30 thousand square meters were practically ready.

This was reported by the agency France-Presse (AFP) on November 27.

Inspectors visited the construction site on November 26. At the time of the inspection, about 300 workers were on site and were ordered to stop construction work.

The project is being implemented by Google's subsidiary, Crystal Computing, on the territory of the Ecopôle industrial park in southern Belgium.

Dispute over the data center cooling system

In 2024, Google obtained permission to build three buildings with an air cooling system. However, in 2025 the company proposed to combine two buildings into one and switch to liquid cooling using water from the Samber river.

In April 2026, the regional administration approved the changes, but local residents appealed this decision. In August, Wallonia's Minister of Territorial Development and Infrastructure, François Desquennes, rejected the modified project amid concerns about water availability after a long drought.

However, according to the minister's official response to the Walloon Parliament on October 21, the original construction permit remains valid.

Google challenged the refusal in the Belgian Council of State. Consideration of the company's request to suspend the decision of the regional authorities is scheduled for January 7, 2027.

Inspection materials to be sent to prosecutor's office

The intervention of the authorities was prompted by an appeal from the environmental organization Greenpeace. Its representatives stated that satellite images indicate the continuation of construction work despite the rejection of the modified project.

On November 25, Greenpeace announced the launch of an urgent legal procedure demanding a halt to construction. The organization also advocated a moratorium on the construction of hyperscale data centers in Belgium due to their high consumption of water and electricity.

A representative of the Wallonia administration, Nicolas Yernaux, said that materials regarding the detected violation will be sent to the prosecutor's office.

Google, for its part, stated its intention to maintain an open constructive dialogue with the regional government and experts regarding the company's investments in Wallonia.

Google faces obstacles in expanding infrastructure in Europe

In 2025, Google announced plans to invest 5 billion euro in the development of cloud infrastructure and artificial intelligence technologies in Belgium over two years.

Belgium was not the only European country where the company encountered problems in implementing infrastructure projects. In October 2026, the Finnish authorities also demanded a halt to work at two Google sites until a mandatory environmental impact assessment was conducted.

Based on materials from: AFP, Greenpeace, The Guardian, Data Center Dynamics.